Water Programme Zenica and Tuzla


The project, which SECO co-finances with the German Bank for Development (KfW), contributes to ensuring reliable and affordable water supply in the municipalities of Tuzla and Zenica in the Federation of Bosnia and Herzegovina. To a lesser extent the project also support the rehabilitation of the sewerage network in Zenica.

Región/País Tema Período Presupuesto
Bosnia y Herzegovina
Urban infrastructure and utilities
04.12.2010 - 30.09.2021
CHF  12’450’000
Contexto

In Bosnia and Herzegovina, reliable and safe urban water supply is not ensured for the whole population, notably because of old and undersized infrastructure. Besides, municipal utilities in charge of water supply often lack the capacities and financial means to operate and maintain existing infrastructure, not to mention to invest in extending the services. With a budget increase, additional measures to reduce the flood risk were introduced.

Objetivos

Overall, the project aims at securing water supply to the populations of Zenica and Tuzla by rehabilitating and extending the respective water supply systems, and ensuring the sustainability of the investment by providing the water utilities with the capacities to technically and financially operating the water network. Financial sustainability is also secured through a progressive adjustment of water tariffs towards cost-coverage thresholds.

The expected impact of the project is to improve the living conditions of the population in Tuzla and Zenica.

Efectos a medio plazo

To establish a reliable and hygienic water supply for the population in Tuzla and Zenica at a cost covering and socially acceptable price.

Resultados

Resultados previstos:  

Improved water supply in Tuzla, Zenica

Improved wastewater system in Zenica.

Strengthened capacities and efficient operation of the public utility companies in the two municipalities.


Dirección / Officina Federal responsable SECO
Crédito Cooperación al desarrollo
Contrapartes del proyecto Contraparte del contrato
  • KfW banking group
  • Municipalities, Public Utilities


Presupuesto Fase en curso Presupuesto suizo CHF    12’450’000 Presupuesto actual suizo ya emitido CHF    0 Presupuesto inclusive contrapartes del proyecto CHF    25’242’500
Fases del proyecto Fase 2 01.01.2015 - 30.05.2021   (Completed) Fase 1 04.12.2010 - 30.09.2021   (Fase en curso)